Recent Projects
Portfolio
Connecting clients
The Project involved obtaining approvals from MSEDCL for laying of a new electrical line.
The process involved design, selection and erection of transformer and its connected sub-station.
A fully automated control panel with safety features (fire alarms, sprays, lift backup) was part of the installation
Fatigue analysis was as per ASME Sec VIII Div 2 Part 5.
A combination of thermal, structural and seismic loads were considered for the analysis. For thermal analysis, complete convection was simulated for greater accuracy.
Soviet era forging press was imported and its wiring and control system was completely refurbished and modernize.
The project involved complete erection of the press, and resulted in efficiency savings and production improvements